Project: Thái Bình thermal power plant
Location: My Loc, Thai Thuy, Thai Binh
Scope of work: Installation of steam turbine, generators, auxiliary equipment 600MW for power plant.
Duration: 18 month
Value of contract:
Project: Thái Bình thermal power plant
Location: My Loc, Thai Thuy, Thai Binh
Scope of work: Installation of steam turbine, generators, auxiliary equipment 600MW for power plant.
Duration: 18 month
Value of contract:
Project: Nghi Son Refinery and Petrochemical Plant
Location: Tinh Gia, Thanh Hoa
Scope of work: Fabrication and Installation of steel structure, piping, equipment
Duration: 18 month
Value of contract:
Project: Dong Phuong Petroleum Blending Plant
Location: Can Tho
Scope of work:
– Fabrication and Installation of 06 storage tank 500m3
– Fabrication and Installation of steel structure
– Equipment installation: 06 distillation columns, 06 condensate columns, 05 LPG storage tanks 20 ton and pumps
Duration: 12 months (2013)
Project: Extension of petroleum terminal
Location: Lien Chieu – Da Nang
Scope of work: Blasting and painting of petroleum storage tanks and piping system with total area 9,000m2
Duration: 6 months (2012)
Project: Extension of petroleum terminal
Location: Chan May – Hue
Scope of work: Blasting and painting of petroleum storage tanks and piping system with total area 13,000m2
Duration: 6 months (2012)
Project: Shipbuilding blocks H1002
Location: Ba Ria – Vung Tau
Main contractor: F.V.S JSC
Scope of work: Fabrication and installation of 14 blocks (from 16 ton to 60 ton each)
Duration: 12 months (2012)
Project: Nghi Sơn cement corporation – Hiep Phuoc Distribution Terminal.
Location: Hiep Phuđoc – Nha Be
Scope of work:
– Fabrication and installation of steel structure
– Fabrication and installation of 02 hoppers
– Equipment installation: vibrating screen, bucket elevator, air compressors and compressed air piping system
Duration: 3 months (2010)
Project: Power plant of Formosa Corp. (2nd phase)
Location: Nhon Trach – Dong Nai
Main contractor: Lilama 69-2
Scope of work: Installation of boiler, steam drum and steam pipe.
Duration: 3 months (2011)
Project: Van Phong bonded petroleum terminal
Location: Van Phong – Khanh Hoa
Contractor: Hoa Hiep Engineering
Scope of work: Fabrication and installation of storage tanks (2 tanks 10,000m3, 2 tanks 7,500m3, 2 tanks 4,500m3, 2 tanks 1,500m3)
Duration: 6 months (2011)
Project: Vina Kraft Paper Company
Location: My Phuoc 3 Industrial Zone – Ben Cat – Binh Duong
Main contractor: Chien Thang Engineering
Scope of work:
– Installation of steel structure
– Equipment Installation: Boiler (130 ton/hr), steam drum, steam turbine, electrostatic precipitator, stacks
Installation of Piping system and Ducting system
Duration: 12 months (2010)